Before the Budget Is Locked

  • Writer: EARTH TEK GPS
    EARTH TEK GPS
  • Jul 15
  • 2 min read

Why the most important number isn't always the budget itself.


A project crossed my desk recently that looked pretty straightforward. The layout wasn't changing, the number of lots wasn't changing, and the schedule wasn't changing. On paper, there didn't seem to be much left to discuss.


Then we started reviewing the earthwork assumptions.


Within about twenty minutes, we weren't talking about dirt anymore—we were talking about the budget.


That conversation reminded me of something I've seen throughout my career.


Some of the biggest financial swings on a project don't come from major design changes. They come from small decisions that quietly influence every cubic yard across an entire site. A little more stripping. A slightly deeper pond. A different roadway section. A finished floor elevation that moves just enough to change the grading.


Individually, none of those decisions seem significant. Across an entire development, they can change the financial picture in a meaningful way.


That's why I don't think the most important question early in a project is, “What does the earthwork cost?”


I think it's, “How confident are we in the assumptions behind that budget?”


There's a difference.


One asks for a number. The other asks how much confidence you should have in that number.


In my experience, that's where the most valuable conversations happen. Not because anyone has done something wrong, and not because the engineer, designer, or contractor missed something. Early budgets are built on assumptions, and understanding which assumptions carry the greatest financial impact helps everyone make better decisions.


I've found that the goal isn't to eliminate uncertainty. That's impossible. The goal is to understand which unknowns are worth digging into before the budget becomes the benchmark everyone starts working from.


A Question Worth Asking


The next time you're reviewing an early site budget, ask one question:


If one assumption changes, which one has the biggest financial impact?


The answer may not change the project.


But understanding it might change the decision.


Bill Cheatham

President | Earth Tek

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.

Want The Dirt Uncovered delivered to your inbox?

Get the latest issue and practical earthwork insights from Earth Tek.

Subscribe to our newsletter • Don’t miss out!

bottom of page